Search
Adapted for people with disabilities

News

print

The first phase of the rehabilitation of distributary irrigation scheme comes to an end

Georgian Amelioration LLC  has completed the first phase of the rehabilitation of the distributary irrigation scheme fed from the Nadarbazevi reservoir in Gori municipality. The Minister of Environmental Protection and Agriculture Mr. Otar Shamugia together with the State Representative of the Shida Kartli region, Mr. Mikheil Shakhulashvili and General Director of the "Georgian Amelioration" LLC Mr. Tengiz Nasaridze paid a visit to Gori municipality to get information about the accomplished works. Currently, 6 projects worth GEL 6.3 million are being launched in the region, after the completion of the rehabilitation activities, 2,740 hectares of farmland will be irrigated regularly.

 

" The farmers should irrigate their agricultural land areas to get a high-quality, abundant harvest and make extra income. Thence, we are spending tens of millions for the development of irrigation infrastructure both from the state budget and from Donor Support Programs.
A few years ago, we restored the pumping station in the Shida Kartli region which files the Nadarbazevi Lake reservoir, thereafter,  we started organizing /arranging the irrigation infrastructure. 

 

The part of the construction has already been completed and up to 1000 hectares of agricultural land have been provided with irrigation water in the villages of Nazalevi, Khurvaleti, Chobalauri, Nigoza and Zemo Rene. We continue construction activities and further development of the project", said Mr. Otar Shamugia. 
Within the project, in total, 14 km of water distribution networks were arranged; including the arrangement of the reinforced concrete lining of tunnel shafts, installation of gutters, and various hydro-technical structures.

The project amounts to GEL 2.7 million. It should be mentioned, that the irrigation system hasn’t been functioning for 30 years in the aforementioned territory.

The second phase of the rehabilitation of the irrigation scheme fed from the Nazalevi reservoir is already launched. The restoration works are being carried out on the water distribution network ( 6.5 km length), as a result, an additional 600 hectares of agricultural land area will be irrigated in the municipality. 
From 2012 up to this time, 92 irrigation infrastructural projects worth GEL 59.5 million have been implemented in the Shida Kartli region. As a result, an additional 17,600 hectares were irrigated, and water supply was provided and improved in more than 15,600 hectares of agricultural land area. 

 

Â